Advance payments in construction are becoming more common, particularly where contractors or subcontractors face significant upfront costs before work can begin.
But what exactly is an advance payment, why might one be used, and what risks should construction businesses consider?
The benefits of advance payments in construction
Essentially, an advance payment is money paid to a contractor or subcontractor before the relevant work or service has been carried out.
There are several reasons why a contractor may request an advance payment, but one of the most common is to help manage cash flow where significant project-specific costs need to be incurred upfront.
For example, a contractor may need to source specialist materials, purchase high-value equipment or secure items that have little or no use outside the particular project.
An advance payment can provide greater certainty that these costs are covered if the project is delayed, halted or circumstances change before the contractor is able to recover those costs through normal progress payments.
In some circumstances, advance payments may also be used to secure a contractor’s time or resources, although this tends to be more common on smaller or residential projects.
The risks of advance payments
Advance payments also create risk for the party making the payment because some financial liability is transferred from the contractor to the client before the relevant work has been completed.
For this reason, any advance payment arrangement should be clearly documented within the construction contract.
The contract should set out matters such as:
- the amount of the advance payment;
- what the payment is intended to fund;
- when it will be paid;
- how it will be recovered through subsequent payments; and
- what happens if the contractor does not deliver the agreed work or materials.
The greater the advance, the more important it becomes for both parties to clearly understand their obligations and the protections available to them.
How advance payments can be managed
In basic terms, an advance payment provides funds before the contractor has delivered the corresponding work or goods. The mechanism for recovering that payment should therefore be clearly documented.
Where an advance payment is specifically being used to purchase materials or plant, a client may require a vesting certificate.
This can provide evidence that ownership of specified goods transfers to the client following payment and that those goods are appropriately identified and separated from the contractor’s own assets.
Another mechanism is an advance payment bond or guarantee.
This provides additional protection if the contractor subsequently fails to deliver the work or goods covered by the advance payment.
The appropriate approach will depend on the contract, the value and purpose of the payment and the risks involved. Construction businesses should obtain appropriate professional advice when establishing these arrangements.
The disadvantages of advance payments
Even where contractual protections are in place, advance payments can create practical disadvantages.
Payment is often one of the mechanisms available to a client to encourage work to be completed in accordance with the contract. Once a significant amount has already been paid, some of that commercial leverage may be reduced.
For example, a contractor may have used an advance payment to purchase project-specific materials but subsequently be delayed in mobilising to site. The client may own or have rights over the materials, but that does not necessarily solve the underlying project delay.
Advance payments can also affect the client’s own cash flow by bringing expenditure forward.
There are therefore circumstances where an advance payment can help a project proceed without placing unnecessary financial strain on the contractor or subcontractor. However, advance payment terms should be considered carefully and supported by appropriate contractual protections and governance.
Advance payment vs Early Payment: what’s the difference?
Although the terms sound similar, an advance payment and an Early Payment request on an approved progress claim are not the same thing.
An advance payment generally provides funds before the relevant work or service has been completed.
Early Payment in Payapps applies to a progress claim that has already been submitted and approved. It gives an eligible subcontractor the option to request payment before the normal contractual payment date.
That distinction is important. Early Payment is not intended to replace a main contractor’s obligation to pay subcontractors according to agreed payment terms. Paying approved claims on time should remain the baseline.
Instead, Early Payment provides an additional, optional cash-flow choice for subcontractors who may want access to an approved payment sooner.
The need for that flexibility is understandable. Recent Payapps research found that only 8% of subcontractors said all their progress claims are paid on time, while 40% said they would be interested in an optional early payment arrangement on approved claims. Read more about how late payments are affecting subcontractor cash flow and builder margins in Inside Construction.
For main contractors, the Payapps Early Payment feature brings those requests into the existing progress claim workflow. Builders can control which projects and subcontractors are eligible and define the available payment timeframes and discounts, while subcontractors decide whether they want to request the option.
This provides a more structured alternative to managing early payment requests through separate emails, phone calls or one-off project arrangements.


